A section of Manhattan's Anderson Avenue will close to through traffic for nearly two weeks starting Wednesday as crews pave westbound lanes for an ongoing utility and street overhaul.

The Phase 2B closure, stretching between College Heights Road and Elling Drive, is scheduled to last from Nov. 11 through Nov. 20. While through traffic will be prohibited, local access will remain open.

Motorists can reach Willard Place, Wildwood Lane, and Professional Place businesses from the east, while the Wildcat Ridge area and Unger Complex can be accessed from the west via Timberlane Drive.

The paving marks the latest step in a $10.61 million, 13-phase infrastructure project by Bayer Construction that is scheduled to continue through 2027.

Funded largely by $4.85 million in gas tax revenues and a $2.7 million federal American Rescue Plan Act grant, the broader initiative will replace more than a mile of undersized, 1940s-era water mains and install a portion of a new 24-inch cross-town transmission main.

The multi-year project — which is also supported by $3.06 million in city water and stormwater funds — includes completely replacing the corridor's concrete pavement, rehabilitating structurally deficient curb inlets, and widening sidewalks to improve accessibility.